FoDDC Building Control Site Inspection Schedule Revision 4: April 2013 |
Site inspections are normally carried out by Building Control at key stages to ensure the works are being carried out in compliance with the Building Regulations. Please note it is your responsibility to ensure that Building Control is called at commencement of work, as well as the stages of work they have asked to inspect which are typically shown below. Inspections are made at the discretion of the Building Control Surveyor for your area and can be contacted as shown below. Additional inspections may be requested, or carried out at the same time as others or omitted depending upon the type, scope and scale of the works.
Building Control Surveyor and area covered | ||
Area/Parish | Surveyor | Surveyor contact details |
Bromsberrow, Corse, Drybrook, Dymock, Gorsley, Hartpury, Kempley, Kilcot, Oxenhall, Pauntley, Upleadon, Redmarley, Ruardean, Rudford, Staunton (North), Tibberton. | Aldo Giovanelli MBEng | T: 01594 812361 M: 07748 118636 E: aldo.giovanelli@fdean.gov.uk |
Awre, Blaisdon, Cinderford, Churcham, Huntley, Littledean, Longhope, Mitcheldean, Newnham, Ruspidge, Taynton, Westbury on Severn | Mark Saunders MRICS | T: 01594 812357 M: 07796 548680 E: mark.saunders@fdean.gov.uk |
Coleford, English Bicknor, Lydbrook, West Dean (Berry- Hill, Bream, Christchurch, Ellwood, Milkwall, Oldcroft, Parkend, Pillowell, Sling, Viney- Hill, Whitecroft, Yorkley) . | Simon Drake BSc, MRICS | T: 01594 812360 M: 07796 548681 E: simon.drake@fdean.gov.uk |
Alvington, Aylburton, Beachley, Hewelsfield, Lydney, Newland, Redbrook, St Briavels, Staunton (South), Stroat, Tidenham, Tutshill, Woolaston | Tony Gwynne MRICS, MIFireE | T: 01594 812355 M: 07796 548682 E: tony.gwynne@fdean.gov.uk |
Site inspections for stage of work and notice required | ||
Stage of Work | Notice required | |
1. | Commencement | 2 working days before |
2. | Foundation excavation before pouring concrete | 1 working day before |
3. | Ground floor oversite before covering or pouring concrete | 1 working day before |
4. | Before covering drainage over | 1 working day before |
5. | Before covering over structural elements, upper floors and roof | |